Norfolk Southern’s production team starts Railroad Crossing work on Monday, May 6th in Fairview
Norfolk Southern’s production team starts on Monday, May 6th near Fairview PA working towards East Springfield PA. The plan is to tear the crossings out and have them back in the same day, but depending on track time and other factors, it could take 48 hours to get some of the crossings back in and opened back up.
Below is a TENTATIVE schedule for the road closures:
DIV | PREFIX | MP | TRACK | DOT# | TYPE | ROAD NAME | CITY | COUNTY | STATE | tentative dates |
KS | B | 96.113 | MAIN1 | 471921H | Public | MANCHESTER ROAD | FAIRVIEW | ERIE | PA | 5/6/2024 |
KS | B | 96.796 | MAIN1 | 471922P | Public | OLD DUTCH ROAD | FAIRVIEW | ERIE | PA | 5/6/2024 |
KS | B | 97.7 | MAIN1 | 471923W | Public | EATON ROAD | FAIRVIEW | ERIE | PA | 5/6/2024 |
KS | B | 100.068 | MAIN1 | 471925K | Public | BLAIR ROAD | FAIRVIEW | ERIE | PA | 5/7/2024 |
KS | B | 100.832 | MAIN1 | 471926S | Public | FAIRPLAIN ROAD | GIRARD | ERIE | PA | 5/8/2024 |
KS | B | 102.32 | MAIN1 | 471930G | Public | HAGERTY ROAD | GIRARD | ERIE | PA | 5/9/2024 |
KS | B | 102.651 | MAIN1 | 471931N | Public | MECHANIC ROAD | GIRARD | ERIE | PA | 5/13/2024 |
KS | B | 104.58 | MAIN1 | 876678S | Public | ELK PARK RD | GIRARD | ERIE | PA | 5/13/2024 |
KS | B | 104.969 | MAIN1 | 471937E | Public | MIDDLE ROAD | GIRARD | ERIE | PA | 5/13/2024 |
KS | B | 105.747 | MAIN1 | 471938L | Private | PRIVATE | EAST SPRINGFIELD | ERIE | PA | 5/14/2024 |
KS | B | 106.344 | MAIN1 | 471939T | Public | MIDDLE / TOWNLINE | EAST SPRINGFIELD | ERIE | PA | 5/14/2024 |
KS | B | 106.755 | MAIN1 | 876679Y | Private | FARM X-ING | EAST SPRINGFIELD | ERIE | PA | 5/14/2024 |
KS | B | 107.162 | MAIN1 | 471940M | Public | LUCAS ROAD | EAST SPRINGFIELD | ERIE | PA | 5/15/2024 |
KS | B | 107.326 | MAIN1 | 471941U | Public | HAPPY VALLEY RD | EAST SPRINGFIELD | ERIE | PA | 5/15/2024 |
KS | B | 107.45 | MAIN1 | 471942B | Public | DEPOT ROAD/SR 215 | EAST SPRINGFIELD | ERIE | PA | 5/15/2024 |
KS | B | 108.9 | MAIN1 | 471943H | Public | SCOTT ROAD | EAST SPRINGFIELD | ERIE | PA | 5/16/2024 |
KS | B | 109.719 | MAIN1 | 471944P | Nash | EAST SPRINGFIELD | ERIE | PA | 5/16/2024 |
The team works Monday- Thursday for ten hours a day. They may have to pave on Friday to get crossings that take a little longer open, but hopefully, we can stick to the same-day schedule. This schedule again is tentative and could change due to track time and other factors. Please let me know if you have any questions or concerns.